Still Slow Progress

As the year draws to a close it is evident that the workers are eyeing the holiday season as very little progress is being made. One of the holdups is with the Guttering which was promised for last week but now is expected to arrive next week. This has delayed the outside painting.

Door frames are being painted, so the inside is slowly taking shape. Master bedroom bathroom and communal bathroom tiling is completed. Powder room is virtually finished apart from shower, not sure on where hot water supply comes from and notice that light switches are inside bathrooms, which can be a cause of electrocution and is banned in UK, but of course we are in the Philippines where health and safety have little bearing on the matters.

Whilst we were in Dipolog we choose the various light fitting, it was a bit chaotic not knowing exactly where the fitting would be placed as we did not have the lighting plan with us, so we will be in for a surprise on our next visit to our Dipolog house and Lot for Sale.

We have now been promised a date in January for completion, so can now start sourcing furniture in the year end sales, so long as the shops are prepared to store it until our house is complete.