Site VisitToday we are seeing progress again on our Diplog house and lot. The upper floor has been laid by I am a little worried about the many cracks in the concrete, I am not sure the mixture was right. Work has started on the shuttering of the upper floor
We might have a problem with the bathroom and have asked that the architect checks the dimensions of the bath we have ordered to see that it in. It seems raising the riot act last week may have got them back on course to complete by 7th December.
The site next to us has been sold and a start has been made on clearing the site, however the excavator has removed some of the soil from our lot, so now we have a sloping front garden, down to the road level when we wanted the garden to be the above the road . So we have requested the soil be replaced, whist the excavator is still on site.
We were in a bit of a rush as Jasmin had a plane to catch, but we will revisit on Thursday for another update.